Cookies
We use cookies to give you the best possible experience on our website. You are free to manage this via your browser setting at any time or through the find out more link.
Close
Find out more
Cookie Portal
Manage and find out more about the cookies used on this website.
View Cookie Settings
Read Cookie Policy

Accept All Cookies and Close
Close Without Saving
< Back
This website has 4 types of cookies:
Your preferences will not take affect until the "save and close" button is clicked. To view our cookie policy please click here.
Strictly Necessary Cookies Used to help you move around the site and use its features. Without these cookies, it will be very hard to use the website.
Analytical/Performance Cookies Used to anonymously track visitors around the website so that we can improve your experience.
Functional Cookies Allows the website to remember your preferences and personalised your experience.
Targeted Marketing Cookies Allows adverts you see to be targeted to you and your interests.
Save and Close
< Back
< Back
Cookie Policy
< Back

A133 Ipswich Road/Harwich Road improvement scheme, Colchester

Latest News - 14 October 2019: Ipswich Road/Harwich Road Update #41

The hoarding works on the Network Rail side of Ipswich Road roundabout is now expected to start around mid november. These works will be carried out at weekends and during the night. The traffic management will be installed and removed nightly. There are currently no more planned road closures until the new year.

Please see the latest update in the video below.  

Highway Schemes Homepage

Works Location

 Photos

 

Ipswich Road roundabout 

 

 

Harwich Road roundabout 

A133 Ipswich Road/Harwich Road improvement scheme, Colchester


About the scheme

We are pleased to announce that Eurovia have been awarded the contract and have begun construction of this improvement scheme in September 2018 and are planned to remain on site until Summer 2020. The work start date has changed however the expected duration is planned to remain the same.

The scheme will see the replacement of the double roundabouts located at Ipswich Road and Harwich Road with a single roundabout at each location. The carriageway between Ipswich Road and Harwich Road junctions will also be widened to accommodate two formal lanes in each direction. The scheme will include upgrading existing pedestrian crossings to signal controlled crossings and general improvements to the current off-carriageway cycle and footway provisions.

The scheme will improve the performance of these two key intersections on the A133 and renewal of the infrastructure will reduce maintenance costs. It will also improve the existing highway assets including the strengthening of two retaining walls, one between Ipswich Road roundabout and the adjoining railway line and another between Ipswich Road roundabout and the Waitrose Car Park. The Scheme has also supported the Cowdray Bridge refurbishment, now being progressed separately through the structures capital maintenance programme.

It is recognised that this is a traffic sensitive site and local residents and businesses will have a keen interest in the work phases and traffic management.   With this in mind, we held a ‘Meet the Contractor’ drop-in session with the Eurovia team to discuss the arrangements in place on Wednesday 5th September 2018.  We were pleased with the turnout and received positive feedback, especially around the road layout, crossing upgrades, the new zebra crossing and the new slip lanes. We hope that we were able to reassure residents and provide contacts for any future correspondence.

Various temporary Road closures will be required during the project, the sections of road affected will be Ipswich road (to the south and the north of the roundabout) and Harwich Road (to the south of the roundabout). Directly affected residents/businesses will be notified in advance through letter drops and signage on site. Also we will be making a continued effort to support all communications by putting updates out via our website and Social media. A single road only to be shut at any one time. 


 

Project Timeline 

 

How will it affect you?

Whilst efforts will be made to keep traffic congestion to a minimum throughout these improvements, it is recognised that works will be undertaken in traffic sensitive areas and there is likely to be disruption to normal traffic flows.  Motorists are advised to allow extra time travelling through the area.

To view information regarding other works in the area please also visit www.roadworks.org.

Pedestrian diversions will be in place where necessary and advertised locally.

Frequently asked questions 

Click on the question to reveal/hide the answer:

Why do you have to have so many barriers to close lanes when work is not taking place in that area?
Why can’t you remove the barriers in one area of the site while you work on another?
Where can I find the traffic management information?
Why is the traffic management changing during the project?
Why are you closing pavements and cycleways during phases of the work? As a pedestrian or a cyclist, how do I find information on safe ways through the works?
Why will it take so long to do the work?
Why can’t you have more people working on more of the site to reduce the total time taken for the works?
Why do you think one roundabout will be more efficient and safer than the mini-roundabouts currently?
Why can’t you work nights and weekends to speed up the work and reduce delays?
What sort of work do you have to do that adds up to the works long duration?
Where can I find out what you’ve done and what works will be happening next week and after that?
Did you plan for the level of congestion, disruption and delays affecting the area when you planned the scheme?
What is the real cost of the scheme to ECC?
Is the Ipswich Road closure needed and why is it longer than previous closures?
What is involved in the piling works?

Further information

Updates will be available via this webpage including changes to the work programme, updated frequently asked questions, details regarding traffic arrangements such as temporary closures as well as local signage and information will also be available on our twitter feed @essexhighways

If you have any queries, please contact the Essex County Council customer services team by telephone: 0345 603 7631 or by completing the online form www.essex.gov.uk/enquiries