Fullbridge/Station Rd Roundabout surfacing works planned overnight Sunday 21 June


18/06/2020
Progress Update
Latest information relating to Market Hill/Fullbridge surfacing improvements in Maldon

Read more

Maldon - Market Hill / Fullbridge carriageway improvements

[FEATURED_NEWS]

Works Location

 

Photos

About the scheme

Road surface improvements are planned to take place on Market Hill and Fullbridge in Maldon during June 2020.

These works have been combined with waterproofing the bridge deck, which carries the road over the River Chelmer, to help preserve the life of the bridge. 

Traffic flows are still generally lower than normal at the moment due to the Coronavirus (Covid-19) and we have been able to fast track our plans and combine works to utilise this quieter time to minimise inconvenience to residents and work efficiently. 

The works are anticipated to take two weeks to complete.  

The majority of which will be carried out overnight with the support of overnight road closures, although a full closure of the bridge will be required for two days, to support bridge waterproofing activities as the waterproofing process can only be done traffic-free.

What is involved and how this may it affect you

Surfacing improvements are scheduled to begin on Monday 8 June 2020 with work being carried out in phases between Market Hill (where it meets the High Street) and Fullbridge/Station Road roundabout (near Tesco/Lidl stores).  

The majority of the works will take place overnight Monday to Friday, with the support of temporary road closures with the road reopening during the daytime. However, when waterproofing the bridge deck, currently planned overnight on Wednesday 9 June through to 5am Saturday 13 June, it will be necessary to close the road, with no vehicles permitted to pass over the bridge. 

A limited number of closures on Maldon High Street will be required.

During the works there will be occasions when a temporary road surface will be in place. Drivers are advised to pay particular attention to sign onsite and to allow extra travelling time for journeys in the area. When roads are closed, no access will be possible to through traffic due to the nature of the activities being carried out. 

A formal diversion (suitable to all vehicles) will be signposted during road closures. Visit one.network for details.

Pedestrian access will be maintained throughout.

Proposed traffic management restrictions are outlined below however please be aware that the work programme may be subject to change if affected by poor weather or if unexpected issues arise. The latest updates will be reflected on site signage and this webpage.

Phase No.   Proposed phasing  Proposed traffic restrictions
Market Hill – surfacing 
Thursday 18 June – night works 8pm to 5am 
- Closure of High Street (from Gate St to North St)
- Closure of Market Hill up to Fullbridge/Station Road roundabout. 
- Tesco/Lidl access unaffected by works
Fullbridge Road and Market Hill (between Cromwell Hill and Anchorage Hill) – surfacing 
Friday 19 June – night works 8pm to 5am 
- Closure of Market Hill up to Fullbridge/Station Road roundabout. 
- Tesco/Lidl access unaffected by works
10  Fullbridge/Station Roundabout (by Tesco/Lidl) - roundabout surfacing
Sunday 21 June - night works 7pm to 5am
- Closure of Market Hill up to Fullbridge/A414/The Causeway roundabout
- Resident access via High Street/Market Hill only
11 Fullbridge Road – high friction surfacing
Monday 22 June - night works 8pm to 5am 
- Closure of Market Hill up to Fullbridge/Station Road roundabout.
- Tesco/Lidl access unaffected by works
Note:  
A limited number of High Street road closures are required (refer to Document Section for High St diversion)
Closure start times vary to accommodate access to nearby stores on Fullbridge

 

Vehicle access to properties

No through traffic will be permitted into our work area during closures however properties located within the closed road will remain accessible, supported by the onsite team. For the safety of the public and operatives carrying out the works it is important that we keep vehicle movements to a minimum. 

Please note that during the bridge works, no vehicles will be permitted to pass over the bridge and access to properties will be from either side of the bridge.

 

Passenger transport

Bus operators have been informed about the works so that adjustments can be made to their services during planned road closures. Please check with the operator for their latest travel information.   

Outlined below are services that may be affected:

Bus Service Route Contact
73 First Maldon to Chelmsford www.firstgroup.com/essex
75 First Colchester to Maldon www.firstgroup.com/essex
90 Stephensons Witham to Maldon  stephensonsofessex.bushub.co.uk
95 Hedingham Tollesbury to Maldon www.hedingham.co.uk
288 Stephensons  Town Circular stephensonsofessex.bushub.co.uk
D1 Hedingham  Bradwell on Sea to Maldon  www.hedingham.co.uk
D2 Hedingham Southminster to Maldon  www.hedingham.co.uk

Please refer to the Document Section below for information to be displayed at the following bus stops: The Swan Hotel, Wantz Road, All Saints Church, The White Horse.

 

No Parking/Clearway

Local Clearway/No Parking zones will be in place to prevent on street parking which may impact our works or access by our large plant/machinery.

 

Further information

Residents and businesses directly affected by these works are being contacted directly.

Updates, traffic management and access information will be reflected on local signage and this webpage as information becomes available.

You may also wish to follow @essexhighways or view one.network for information about other works in the area.

Please be aware that the work programme may be subject to change if for example if affected by poor weather, if other unexpected issues arise including Government advice associated with Covid-19.

Thank you for your patience while we carry out these improvements.