Cookies
We use cookies to give you the best possible experience on our website. You are free to manage this via your browser setting at any time or through the find out more link.
Close
Find out more
Cookie Portal
Manage and find out more about the cookies used on this website.
View Cookie Settings
Read Cookie Policy

Accept All Cookies and Close
Close Without Saving
< Back
This website has 4 types of cookies:
Your preferences will not take affect until the "save and close" button is clicked. To view our cookie policy please click here.
Strictly Necessary Cookies Used to help you move around the site and use its features. Without these cookies, it will be very hard to use the website.
Analytical/Performance Cookies Used to anonymously track visitors around the website so that we can improve your experience.
Functional Cookies Allows the website to remember your preferences and personalised your experience.
Targeted Marketing Cookies Allows adverts you see to be targeted to you and your interests.
Save and Close
< Back
< Back
Cookie Policy
< Back

Church Farm Culvert, High Street, Stebbing

Highway Schemes Homepage

Works Location                     

 

 

Photos

 





About the scheme

Church Farm Culvert is a brick arch structure located under the High Street in Stebbing, Uttlesford.  It consists of two structures, made from two separate construction methods which carries the road over an unnamed stream.

The culvert is in an unstable and deteriorating condition that requires replacing. The east bridge headwall is leaning away from the carriageway which has resulted in brick loss to the headwall’s face.  A ‘Give and Take’ priority arrangement remains in place as temporary measure.

Planning permission (planning application PP-07684645) is now granted.

We are now in a position to begin works on 6th January 2020, and are making preparations on this basis. 

Advance works

UKPN are planning to carry out diversions to electrical supplies prior to any main works. A temporary full road closure will be in place from Monday 2 December 2019 for approximately two weeks.

Proposed culvert works

We will remove both arches and headwalls of Church Farm Culvert, and replace the culvert with a new precast reinforced concrete box unit. This work is regarded as an efficient and cost effective option to bring the structure up to current standards, protecting its future use. We currently estimate these works will take approximately five months to complete, subject to the works not been impacted by poor weather or unexpected issues arising.

A full closure of the High Street at the structure is required, 24 hours a day until the works are complete from Watch House Road for approximately 180 metres.

Advanced warning notices will be in place prior to any works and appropriate diversions in place during any road closures.

Some Clearway/No Parking areas have been identified to support traffic flows in the area to ensure safe manoeuvres can be carried out by large vehicles such as buses and emergency services.

Access to properties and businesses will be available from either side of the closure point, either via a formal diversion or local alternative routes. Information relating to pedestrian access and arrangements for bus passengers, will be communicated at a later date.

As soon as arrangements are confirmed, further updates will be made to the website.

Further information

Our intention is to keep the community and local parish informed of details as information becomes available and the scheme progresses. The latest information will be reflected on this webpage as well as being shared with the parish and local councillors for them to share more widely.

Please note that dates and work programmes can be subject to change if affected by poor weather or if unexpected issues arise.

You may wish to follow the Essex Highways twitter feed: @essexhighways or find out about other works in the area by visiting one.network (formerly roadworks.org).