Brentwood High Street - road surface improvements

Aerial view of Broad Street Green

Works location and photos

Aerial view of Maypole Road
Brentwood High Street prior to gas works and new road surface
Brentwood High Street prior to the works

Works are being carried out in collaboration with Cadent Gas

Press logo to link to Cadent's webpage

Cadent Gas: Map of proposed work phasing

About the scheme

During autumn 2025, Essex Highways will carry out road surface improvements on a section of Brentwood High Street. The project is being carefully coordinated with Cadent Gas, who will be upgrading gas mains along the same route. By aligning both sets of works, we aim to reduce disruption and deliver improvements more efficiently.

Essex Highways will remove the existing granite setts from the carriageway between Crown Street and St Thomas Road, replacing the surface with asphalt. This decision, made in consultation with Brentwood Council, will result in a smoother and safer road surface for all users.

Our resurfacing programme will follow Cadent’s infrastructure upgrades, making use of their planned road closures. This approach helps minimise future inconvenience for local businesses, residents, and visitors.

Please note: Cadent will repair any areas affected by their gas pipe replacement works that fall outside Essex Highways’ resurfacing scope, including footways. 

How it may affect you

Cadent will commence works to upgrade their gas pipes on Brentwood High Street from 15 September 2025, with the project expected to last approximately six weeks. To support these activities, temporary road and lane closures will be necessary as indicated on the above map.

These works will be delivered in phases, allowing Essex Highways to follow closely behind Cadent with resurfacing operations. This coordinated approach makes use of existing traffic restrictions, helping to minimise disruption for residents, businesses and shoppers.

Essex Highways is scheduled to begin resurfacing on 22 September 2025, which will continue for approximately four weeks. The improvements will focus on the granite sett section of the carriageway between Crown Street and St Thomas Road, replacing the surface with asphalt to enhance safety and providing a smoother surface. Due to the nature of our work, no vehicles will be permitted to pass through the road closure during resurfacing operations (indicated in red on the map above).

Please be aware that our activities are likely to generate noise from machinery and resurfacing equipment. Some disruption will be unavoidable during the improvement works, and we apologise for any inconvenience this may cause. 

Please note that the schedule may change if affected by poor weather or if unforeseen circumstances arise.

Further information

Visit Cadent’s Brentwood High Street - works and traffic management information for further details.

Additional details can be found in the Document Section below.

To view other roadworks in the area, visit One.Network.

Contact information - Cadent Gas

If you have a question relating to Cadent Gas works then they can be contacted on 0800 0854 478, alternatively on-site support will be available to assist with any specific access requirements.