Cookies
We use cookies to give you the best possible experience on our website. You are free to manage this via your browser setting at any time or through the find out more link.
Close
Find out more
Cookie Portal
Manage and find out more about the cookies used on this website.
View Cookie Settings

Accept All Cookies and Close
Close Without Saving
< Back
This website has 4 types of cookies:
Your preferences will not take affect until the "save and close" button is clicked. To view our cookie policy please visit our cookie policy page.
Strictly Necessary Cookies Used to help you move around the site and use its features. Without these cookies, it will be very hard to use the website.
Analytical/Performance Cookies Used to anonymously track visitors around the website so that we can improve your experience.
Functional Cookies Allows the website to remember your preferences and personalised your experience.
Targeted Marketing Cookies Allows adverts you see to be targeted to you and your interests.
Save and Close
< Back
< Back
Cookie Policy
< Back

A1245 Chelmsford Road/Rawreth Lane/Church Road, Rayleigh – Traffic signal renewal  

Highway Schemes Homepage

Works Location


Photos

View of existing traffic lights from High Road

 View of existing traffic lights from High Road

The works

Arrangements have been made to renew the traffic signals at the junction of Chelmsford Road, Rawreth Lane, Church Road, Rayleigh.

Works are due to start on Monday 14 September 2020 and expected to take approximately seven weeks to complete.

We will be replacing the traffic signals at the junction before they become unreliable and fail to work properly and will be installing new extra low voltage equipment which will help reduce our carbon footprint.


What is involved and how it may affect you

Works will be carried out between 7pm to 5am, Monday to Friday. To manage traffic during the works a combination of lane closures, closures of individual approaches and a number of full junction closures will be required.

The junction closures required will be implemented in four separate phases and will be required for each of the four approaches to the junction (A1245 Chelmsford Road Southbound, Rawreth Lane, A1245 Chelmsford Road Northbound and Church Road). Please be advised only one closure will be active at any one time to minimise disruption.

To view details of the proposed phases please refer to the document section below. Please note phases may not run in order.

Advanced warning notices will be in place prior to any works commencing and appropriate diversion routes will be implemented during closures.

During non-working hours, traffic management restrictions will be lifted where possible to allow the temporary traffic lights to work in a similar way to the existing signals to control traffic at the junction.

Pedestrian access will be maintained at all times and for safety, we propose to install temporary controlled pedestrian crossing across Chelmsford Road.

Access to properties on Bedloes Avenue will be maintained during the closure of the A1245 Chelmsford Rd southbound by mean of manual control/gatemen.



Further information

Dates may be subject to change if affected by poor weather conditions or if unexpected issues arise.

We aim to keep residents and businesses updated via this webpage and site signage. Information will also be shared with the local parish councils.

For details about other roadworks in the area, please visit: one.network or the @essexhighways twitter feed.