Cookies
We use cookies to give you the best possible experience on our website. You are free to manage this via your browser setting at any time or through the find out more link.
Close
Find out more
Cookie Portal
Manage and find out more about the cookies used on this website.
View Cookie Settings

Accept All Cookies and Close
Close Without Saving
< Back
This website has 4 types of cookies:
Your preferences will not take affect until the "save and close" button is clicked. To view our cookie policy please visit our cookie policy page.
Strictly Necessary Cookies Used to help you move around the site and use its features. Without these cookies, it will be very hard to use the website.
Analytical/Performance Cookies Used to anonymously track visitors around the website so that we can improve your experience.
Functional Cookies Allows the website to remember your preferences and personalised your experience.
Targeted Marketing Cookies Allows adverts you see to be targeted to you and your interests.
Save and Close
< Back
< Back
Cookie Policy
< Back

Mundon Wash Bridge, Mundon Road, Mundon, Maldon

Road Closure - 06 April 2020: Mundon Wash Bridge – full road closure on Blind Lane, Mundon

The works programme has been amended and the road patching activities to repair identified defects on Blind Lane have been brought forward by one week. These works will start on Monday 6 April 2020 and anticipated to take two weeks to complete.

Due to the restricted road width, a full closure on Blind Lane will be in place for the duration of the works. 

• Week commencing 6 April: Blind Lane will be fully closed 24 hours a day (no through traffic). 

Access to properties on Blind Lane during closure periods will continue to be maintained either from Fambridge Road or Mundon Road, depending on the location of the repairs. Advance signage will be in place to advertise the road closure with appropriate diversions in place.

We appreciate that these works may cause temporary inconvenience, and would like to apologise for this.  

Please note that the work programme may be subject to change if the works are affected by poor weather or if unexpected issues arise.

Thank you in advance for your patience and co-operation while we undertake these necessary works.

Highway Schemes Homepage

Works Location


Photos

Above: View of the carriageway from the south 



Above: West elevation of the existing concrete box culverts

Above: West elevation of the concrete pipe structure


About the scheme

Mundon Wash Bridge carries Mundon Road over the Mundon Wash waterway in Mundon, Maldon.

The bridge dated back to the 1940s and consisted of three sections, two reinforced concrete box structures and a concrete pipe that run under the carriageway.  An assessment of the structure found the structure to be in a weak condition and required replacing. 

Bridge replacement works have taken place with the support of a full road closure to allow the original structure to be removed and replaced with a combination of two precast concrete box sections which have been placed side by side, along with headwalls and wingwalls that comply with national standards.


The Works 

Mundon Road was closed at the bridge to allow construction work to begin.  The road reopened in December 2019 however some remedial works remain.  These are planned for March 2020 with the support of temporary traffic lights.  

These works are anticipated to start 16 March and take approximately four weeks to complete, after which road patching activities are planned to repair identified defects on Blind Lane, Mundon. 

 

Blind Lane - road closure for road patching works:

Following completion of the outstanding works to Mundon Wash Bridge, road patching activities are planned to repair identified defects on Blind Lane in Mundon.  These works are anticipated to take approximately two weeks to complete from Monday 13 April 2020 with the support a road closure due to the restricted road width.  

  • Week commencing 13 April: Blind Lane will be fully closed 24 hours a day (no through traffic).  
  • Week commencing 20 April: A full road closure (no through traffic) will continue to be necessary on Blind Lane to carry out remaining patching works however in order to accommodate local businesses on Blind Lane, we anticipate limiting these closures times to daytime, off peak hours only.  

Access to properties on Blind Lane during closure periods will continue to be maintained either from Fambridge Road or Mundon Road, depending on the location of the repairs. Advance signage will be in place to advertise the road closure with appropriate diversions in place.

We are contacting businesses on Blind Lane separately to advise them of our plans and to minimise disruption as much as reasonably practicable.

Updates relating to the traffic management plans will be updated to this webpage as the works progress.

We appreciate that these works may cause temporary inconvenience, and would like to apologise for this.  

Please note that the work programme may be subject to change if the works are affected by poor weather or if unexpected issues arise.

Thank you in advance for your patience and co-operation while we undertake these necessary works. 


Further information

The work programme may be subject to change if works are affected by poor weather or if unexpected issues arise.

The latest information and updates about these works, including changes to traffic management will be updated to this webpage and reflected on site signage. 