× Stambridge Road Culvert update
18/08/2021
Latest News

The lining works started as planned at the culvert located on Stambridge Road. As the works have progressed we have been advised it will be necessary for the road closure to remain in place until the end of the day on Friday 20 August 2021.

Read more

Stambridge Road, Great Stambridge - Culvert repairs  

Works location and photos

View of culvert located on Stambridge Road
View of brickwork to be repair

About the scheme

Preparations are being made to carry out essential works to the culvert located on Stambridge Road, Great Stambridge. Activities will include lining works to the culvert followed by brickwork repairs.

Lining is a cost effective and efficient method of carrying out essential works which will extend the life of the culvert. This method also has a low environmental impact and allows us to carry out a full structural repair with minimal disruption to the traffic flow in the area.

What is involved and how this may it affect you

The works will be carried out in two stages with the first stage due to start on Monday 16 August 2021 for approximately 4 days.

Lane restrictions with two-way traffic lights will be in place on Monday 16 August 2021 in order to install a temporary dam. From Tuesday 17 August 2021, Stambridge Road will be closed at the culvert for approximately 3 days while we carry out the lining works.

Following the completion of the culvert lining, brickwork repairs are planned to take place from Tuesday 31 August 2021 for approximately 4 days. During this time there will be lane restrictions managed by temporary traffic lights on Stambridge Road.

The second stage of lining works will be completed later in the current financial year and we will provide a further update as soon as arrangements are confirmed.

Passenger transport

Bus operators have been provided notice of the works so they can make adjustments to their services during the road closure. Passengers who wish to access the service 60 and live south of the road closure will need to contact Arrow Taxi’s who will provide a taxi to connect with the service 60 at either North Street or East Street to continue your journey.

Passengers are required to pre-book two hours before travel by calling Arrow Taxi’s on: 01621 855111.

The bus service north side of the closure will still be in operation but will turn around in Ash Tree Court and reconnect with the normal route.

If you have any queries regarding the passenger transport arrangements please either contact the operator directly, or the Essex Passenger Transport Team on 0345 603 2200. You can also follow the passenger transport twitter account: @Essex_pt 

Further information

Dates may be subject to change if affected by poor weather conditions or if unexpected issues arise.

We aim to keep residents and businesses updated via this webpage and site signage. Information will also be shared with the local parish councils. For details about other roadworks in the area, please visit: one.network or the @essexhighways twitter feed.