Oasis Bridge – update to traffic management arrangements

Due to slight delays with the scaffolding and breaking out of concrete the works programme has been updated and dates have been amended to the traffic management arrangements.

The overnight road closures previously advertised for 31 July and 14 August are no longer required. All dates for traffic management changes are as followed:

Provisional dates
Works and proposed traffic restrictions
 
4 July to 11 July
Double lane closure in both directions to install contraflow
 
5 July
Overnight road closure on A138 from the exit slip to entry slip in both directions for jack and de-jacking bridge
 
12  July to 5 September 2021
Northbound contraflow in place (Southbound closed)
 
19 July 2021
Overnight road closure on A138 from the exit slip to entry slip in both directions for jack and de-jacking bridge
 
5 August 2021 Overnight road closure on A138 from the exit slip to entry slip in both directions for jack and de-jacking bridge  
19 August 2021 Overnight road closure on A138 from the exit slip to entry slip in both directions for jack and de-jacking bridge  
6 September to 24 October 2021 Southbound contraflow in place (Northbound closed)  
25 October to 27 October 2021  Double lane closure in both directions to remove contraflow