East Hill construction update - update 5/08/26

Works on East Hill are now underway and progressing well, following the appointment of Octavius Infrastructure as the main contractor.

Works completed so far:

  • Deep drainage investigation works at the Guildford Road junction
  • Start of installation of the new kerb lines adjacent to Lewis Gardens and east of Priory Street
  • Construction of a temporary pedestrian crossing and pedestrian diversion on the northern footway
  • Removal of the central island on Roman Road
  • Removal of the pathway build-out west of Priory Street

Upcoming works:

  • Continued installation of new kerb lines on the south side of East Hill.
  • Relocation of the coach stop from St James' Church to Stop 'Hb' (outside Minories).
  • Removal of pathway build-out east of Priory Street
  • Zebra crossing widening