16 November 2026 Latest News

St Botolph's Circus - Bus gate suspension trial

Bus gate suspension to be trialled

As works enter their next phase, St Botolph's will need to be reduced to a single lane. This change is required to provide the space needed for the team to safely progress the works.

Throughout the project, the team has been proactive in identifying opportunities to minimise disruption and reduce the impact on traffic wherever possible.

As part of this approach, the project team will be trialling a temporary suspension of the bus gate on St John's Street over the coming weeks in the lead-up to Christmas.

When single-lane running is in operation, traffic leaving Vineyard Street Car Park and the Lion Walk Service Area can sometimes block the junction, preventing buses from accessing St John's Street or Stanwell Street. This can cause traffic to back up around the roundabout and lead to congestion throughout the surrounding road network.

The temporary suspension will allow motorists to turn right into St John's Street, avoiding the need to travel via Southway, or continue straight ahead onto Stanwell Street.

To support the change, the enforcement camera will be suspended, and additional signage will be put in place to guide motorists.

The trial will be monitored to assess its success.