A road improvement scheme to support a key business area in Harlow is on track to be completed next month.
To provide improved, quicker access to the recently completed M11 J7a, a new entrance and exit on the A1184 Cambridge Road has been developed. This will provide additional access to and from the eastern end of the industrial estate.
Additional pedestrian facilities are also being provided, promoting safer, greener and healthier travel in the area.
Overnight road closures have been in place over the last week to undertake resurfacing works.
Following the completion of resurfacing, the next stage of works will see new traffic signals installed, landscaping completed, and then demobilisation from the site.
During this period two-way lights will be required to keep everybody safe. These will be removed as soon as practically possible.