Canvey Island footway repairs in preparation for slurry sealing treatment

Works location and photos
Location to be included in the planned footway upgrades
Illustration of future slurry treatment that will be carried out under a separate work programme
About the scheme
A programme of footway maintenance is about to begin on Linden Way in Canvey Island and surrounding areas to address defects and surface irregularities.
These works are a pre-treatment for future slurry sealing activities that will restore texture and seal the the existing surface, providing a weather protection barrier to prevent further deterioration due to water ingress. These works will ultimately extend the service life of our footpaths.
These pre-treatment activities will begin on 8 June 2026 for phase one works which will continue into the autumn.
Areas currently identified for improvement include:
- Linden Way
- Little Gypps Road
- Willow Close
Significant defects in footway and kerbs will be addressed, as well as surface levelling. These works will be carried out in stages during the daytime, to minimise local inconvenience.
The slurry sealing programme will be carried out at a later date (to be communicated separately).
How the work will affect you
Works are due to start on 8 June 2026 with mobilisation of the site team, with activities phased to minimise local inconvenience.
Provisional dates
(these may be subject to change)
|
Proposed street in Heybridge
|
| Phase one from 8 June 2026 to end September 2026 |
- Linden Way
- Little Gypps Road
- Willow Close
|
| Phase two (dates to be advised) |
|
Most of the time traffic will be managed using a Give and Take arrangement. Traffic marshalls will be on site to provide assistance as required, however we advise drivers to allow extra time to travel through the area.
Please note that dates may be subject to change if the works are affected by poor weather or if unexpected issues arise.
Thank you for your patience while we carry out these improvements.
Clearway/No parking restrictions
Clearways, or no parking zones will be in place to deter vehicles from parking on the street where work activities are taking place. This is necessary to prevent delays that can be caused by restricted access to work area, or hinderance to traffic flows in the area. During these times we respectfully ask that residents seek alternative parking arrangements.
Further information
Residents directly affected by these works will be contacted directly. Updates, traffic management and access information will be reflected on local signage and this webpage as information becomes available.
You may also wish to follow @essexhighways or view one.network for information about other works in the area.