The Albert is a roundabout in North Colchester that connects Colne Bank Avenue, Cowdray Avenue and North Station Road.
It is an important junction as it provides strategic routes for many residents to Colchester Station and Colchester Hospital in the North from the City Centre in the south and vice versa.
This scheme forms part of a wider package of Active Travel projects being undertaken to better connect Colchester, creating east-west and north-south links across the city.
The project was funded by a combination of Active Travel England Funding - money received from the government in 2020/21 dedicated to rolling out new cycling and walking routes across Essex - and Essex County Council investment.
The Albert Roundabout scheme was included in the 2021 Active Travel Fund consultation.
In this consultation, a north-south active travel route (shown on the left) was proposed supporting a better link between the city centre in the south and the main railway station for Colchester in the north.
The Albert Roundabout is an important junction on this route, and this scheme is a step towards the delivery of the complete north-south active travel route.
Support was received for the north-south active travel route in the consultation, with the majority of respondents agreeing that the route would support more cycling and walking in the area.
There were previously a set of shared-use walking and cycling paths and toucan crossings in place. However, the walking and cycling experience was hampered because:
To address the issues, we identified four aims for The Albert roundabout scheme:
To achieve our aims, the project included work on the following:
The below images show the previous site of The Albert Roundabout, alongside artist impressions of what the roundabout looks like now that construction is finished.
Looking west towards the junction from the Cowdray Avenue crossing (eastern arm)
Looking north-west across the junction from North Station Road towards the Colne Bank Avenue Crossing (western arm)
Looking north across the junction from the southern side of North Station Road
The programmes delivery timeline is detailed below.
July – November 2024
Preliminary design
November 2024 – July 2025
Detailed design
October 2025
Award of construction contract
Monday 20 October 2025
Start of construction
February 2026
End of construction
If you have any questions on The Albert Active Travel Improvement Scheme, please contact us via email at activetravel@essexhighways.org.