Due to unforeseen material supply issues and the inclement weather conditions on Tuesday 14 September, the resurfacing works to Churchgate Street roundabout have overrun. 

Unfortunately, utility works by UK Power Network, separate to the project will affect the planned diversion route and now requires a more complex 4-way temporary traffic lights and our resurfacing works to be completed in 3 phases.

Phase 1 - North Side (Old Oak Way) - The team are now on site and works are progressing well and will continue until 6am on Wednesday 22 September.
Phase 2 - Gilden Way towards Sheering - The southeast quadrant will be carried out between 6am on Wednesday 22 September and 7pm on Friday 24 September.
Phase 3 - Gilden Way towards Harlow Town Centre - The southwest quadrant will be carried out between 6am on Monday 27 September and 7pm on Wednesday 29 September.

All dates are subject to weather conditions and the latest Government Covid-19. Thank you for your patience and apologies for any inconvenience caused by these works.