Parkway Corridor, Chelmsford

Latest News - 16 January 2019: Overnight works at Odeon Roundabout commence 21 January 2019

Overnight works are due to start on 21 January 2019 at the Odeon Roundabout starting with the A1099 High Bridge Road/Baddow Road junction improvements situated north of the roundabout, shortly followed by works on Manor Road junction on the south side.

These works are expected to be carried out between the hours of 7.30pm and 6am, Monday to Friday night inclusive.  

Some temporary adjustments will be necessary to road layouts to support access to and from Meadows Q-Park however these will be lifted during the day time.  

There may be periods when temporary traffic management will be required outside of these times to protect the public and working area. 

We would encourage all road users to take additional care when travelling in the area, observe site signage and traffic management in place.

Works Location

 

 

Photos

A1060 Parkway - west of junction with A&N roundabout/flyover to Odeon Roundabout

 

Manor Road with Odeon Roundabout

 

A1099 High Bridge Rd/Baddow Rd (junction with Odeon Roundabout)

 

New London Road/Parkway Junction

 

 

 

About Parkway

Traffic accessing the centre of the city from routes including New London Road, Roxwell Road, Springfield Road, Waterhouse Lane, Broomfield Road, and Chelmer Road usually ends up travelling along Parkway to reach their destination. As a result, the Parkway corridor experiences significant congestion during peak periods, particularly in the city centre and at key junctions along the route. 

There are a significant number of buses which use Parkway (approximately 45 per hour in each direction) and which also suffer from increased journey times and poor journey time reliability as a result of the congestion along the corridor.

This scheme is being delivered as part of the Chelmsford City Growth Package

 

About the scheme 

Essex County Council has secured £15 million to undertake sustainable transport improvements to help alleviate pressure on Chelmsford’s road network.  

Following a public consultation on the Chelmsford City Growth Package during summer 2017, the decision was taken to progress plans for a package of improvements at key locations on Parkway between the junction with the Army and Navy roundabout and flyover and Victoria Road South.

Works are due to start early 2019 to make the following changes (improvements are listed in order travelling from west to east along Parkway):

 

A1060 Parkway - Improvements to road layout westbound (from junction with Army and Navy roundabout / flyover to Odeon roundabout):

We are simplifying the existing road layout and lane markings for westbound traffic exiting from the Army and Navy roundabout and flyover to allow for all three lanes of traffic to continue straight ahead at Odeon roundabout (towards A1060 Parkway westbound).  For traffic travelling from the Army and Navy flyover ahead and continuing westbound on the A1060 Parkway this will reduce the need to change lanes when approaching the Odeon roundabout.

The existing right-turn only lane on the approach to the Odeon roundabout is under-utilised, and this change will help to improve safety and traffic flow for all westbound traffic.

Works will include:

  • modifying existing splitter islands
  • changes to kerbing. 

 

Manor Road junction with the Odeon Roundabout:

This scheme will provide a safer, direct east-west route for people who walk or cycle between Rochford Road east and Rochford Road west. This will improve links to the Moulsham Street shopping area and the Odeon Roundabout subway and connect to the National Cycle Network 1 along the riverside at Kings Head Walk. 

The improvements will allow for safer crossing for the existing cycle route across Manor Road whilst having minimal impact on traffic approaching the roundabout.

Works will include:

  • Installing new directional cycle signage
  • Realigning kerbs
  • An enhanced central refuge on Manor Road, next to the Odeon roundabout.

 

A1099 High Bridge Road / Baddow Road (junction with the Odeon roundabout):

We will be making permanent the existing dedicated left turn restriction for traffic into Baddow Road. This formalises the current temporary restrictions, which have operated since 2011.

To access Baddow Road west from a westbound direction on Parkway, traffic will need to continue to the Market roundabout, U-turn and join the dedicated filter lane to turn left into Baddow Road west. This prevents Parkway through traffic being blocked in peak periods by cars wanting to get to the car parks.

As an additional safety improvement, we will be extending the existing kerb island on High Bridge Road to prevent the movement from the dedicated left turn lane straight onto High Bridge Road. This will help to prevent conflict with traffic exiting Baddow Road west and traffic exiting the roundabout onto High Bridge Road from the outside lane. This will also improve pedestrian safety at the adjacent crossing.

 

New London Road / Parkway Junction: 

At the junction with New London Road, there are long delays in all directions. The following changes will be made to improve travel time through the junction:

  • Extending the existing central reservation to restrict the existing straight-ahead (southbound) and right-turn (westbound) movements of buses from New London Road (north).
  • Widening New London Road (northbound approach) at its junction with Parkway within the existing highway boundary.

These changes will allow traffic in all other directions to keep flowing for longer and should improve overall travel time through the junction by more than 20%.

Over 90% of buses on all approaches to the junction should experience reduced journey times throughout the day, however, a small number of bus journeys from New London Road will take slightly longer in the morning peak period.  All other vehicles are expected to be able to get through the junction quicker.

 

Subways at junction of New London Road with Parkway:

To ensure that north-south cycle journeys on New London Road are not affected by the changes to the junction we will enhancing the existing subways at the junction to provide a safer route across the junction for people who cycle.

 

When will the work take place and how may it affect you?

Works will begin in January 2019 and will be completed in phases. The majority of the works will be completed during the day time (between the hours of 9am and 7pm) during the working week with some Saturday morning working (between 9am and 1pm).

The current works timetable is shown below.   Please note that this information will be updated when more details are available.

Location

Date 

Detail of works 

Odeon Roundabout: 

  • A1099 High Bridge Road/Baddow Road
  • Manor Road

21 January 2019 

Works to commence on north side of Odeon Roundabout initially (High Bridge Road/Baddow Road) shortly followed by works on south side (Manor Road).

Overnight works to take place Monday to Friday inclusive between hours of 7.30pm and 6am.  

Some temporary adjustments to road layouts to support access to/from Meadows Q-Park during these times.

Throughout the various phases, traffic management will be necessary and temporary lane restrictions may be in place.

Please note that advertised dates may be subject to change for example if affected by poor weather or if unexpected issues arise.    

 

Further information

Updates will be available via this webpage including changes to the work programme, details regarding traffic arrangements such as temporary closures as well as local signage.

To view other works in the area please also visit: www.roadworks.org 

This scheme is being delivered as part of the Chelmsford City Growth Package.  For information about other schemes considered visit Chelmsford City Growth Package.